Infrastructure

February 4, 2022

Wittpenn Bridge Project Achieves Substantial Completion

The Wittpenn Bridge project achieved substantial completion on Jan. 17, 2022, another crucial milestone reached by the project team.

Read More

November 12, 2020

Rehabilitation of I-278 Bridges Achieves Final Completion

CCA Civil officially completed the Rehabilitation of I-278 Bridges project in New York on Oct. 31, 2020. This design-build contract with the New York State Department of Transportation (NYSDOT) involved the rehabilitation of four bridges on the I-278 Expressway on Staten Island and one bridge over the Gowanus Expressway in Brooklyn.

Read More

September 29, 2020

Largest Lift-Span Erection Completed on the Wittpenn Bridge

CCA successfully completed the erection and installation of the Wittpenn Bridge’s main lift span, the largest lift span under construction in North America. The team worked two shifts over three days from Sept. 24-26 to complete the work.

Read More

August 25, 2020

New York Gov. Andrew Cuomo and MTA Unveil Underpass at New Hyde Park Road as Part of Third Track

On Aug. 24, 2019, New York Gov. Andrew Cuomo joined MTA officials in New Hyde Park to mark the latest milestone — an underpass running beneath the train tracks — as part of the Long Island Rail Road (LIRR)’s Third Track effort.

Read More

May 5, 2020

Consulate General of PRC in New York Recognizes CCA as a Good Example for Practicing Social Responsibility During Pandemic

A spokesperson for the Consulate General of PRC in New York held up CCA as a good example for practicing corporate social responsibility during the coronavirus pandemic in the remarks themed “Overseas Chinese Enterprises' Projects Maintain Operations Smoothly and Orderly” on April 28, 2020.

Read More

April 20, 2020

Sheaves Erection and Reducers Installation Complete on The Wittpenn Bridge

On April 14, CCA Civil completed the sheaves erection and installation of four secondary reducers on The Wittpenn Bridge. The primary span operating machinery systems have been set on top of the machinery houses. The Wittpenn Bridge project team will continue to work closely with the owner and subcontractors to finalize the machinery house and control house in the coming months.

Read More

October 14, 2019

Macombs Dam Bridge Achieves Substantial Completion

A substantial completion inspection walk-through of the Macombs Dam Bridge project was completed on Oct. 9, 2019, marking a milestone of CCA Civil’s completion of all contractual work for the bridge rehabilitation project.

Read More

June 3, 2019

CCA Civil Completes Replacement of First Rail Road Bridge of LIRR Expansion Project

The replacement of the 66-year-old Cherry Lane bridge was completed on June 3, 2019, marking the first milestone of the Long Island Rail Road (LIRR) Expansion Project.

Read More

July 26, 2018

CCA Officially Seals its First PPP Project–Argentine National Road B Line Franchise

CCA South America officially sealed the $2.13 billion Argentine National Road B Line franchise project along with its joint venture partner GREEN by signing the public-private partnership (P3) contract with the Argentina Government at the Presidential Palace in Buenos Aires, capital of Argentina, on July 26.